Cassandra Clark, Project Communications Director
The upgrade of our Website is now complete, and we are back with more news and information with a renewed vigor. These past two months have seen a bit of a slowdown on our posts and social media program due to summer vacations and transitions here, but we are up and running again — and even more dedicated to making this site informative and useful to our staff, patients, neighbors, community and ever-growing network of friends. If you haven’t yet taken the time to subscribe to our site, I encourage you to do so now. You will receive a notice only when new updates are provided, and we won’t inundate you with e-mails nor solicitations.
The Eden Campus has been alive with activity since we broke ground on July 1. Because of the tremendous progress, we have launched our “Photos of the Week” to complement the WebCam and give you a bit more detail on what the crews are working on.
Below are a few highlights:
Foundation Piers
The crews are continuing to drill and pour the foundation piers, the first phase of the new hospital’s foundation. What does it take for a hospital of this size? Crews will pour 570 piers altogether, some reaching 60 feet underground. They are moving at a rapid pace now, drilling and pouring 10 to 12 piers each work day. Once these are complete — although some work is done concurrently to prep the site — crews will begin work on the underground utilities such as electricity, sewer lines, storm drains and plumbing. They are also beginning installation of the grade beam rebar, and the photo below shows the site excavation and prep work for the rebar.

Temporary Pedestrian Bridge
While work is being done on the site, the current pedestrain bridge will need to shut down. To provide uninterrupted access from the parking garage to the hospital, the crews must build a temporary pedestrain bridge. One the land was excavated, crews placed the braces/beams and began the sheathing of the bridge.


Storm Drain and Fire Road
A new wall is almost complete on the north end of the site, and crews began work on the storm drain. A fire road is also under construction, and this past week the crews continued installation of the fire road retaining wall.


These are just a few highlights of the vast amount of work underway on site. We’ll have DPR Construction, the general contractor, provide more detail on the many phases of the construction.
In the meantime, if you have any questions or comments, we would love to hear from you.






